×

Error

[sigplus] Critical error: The Graphics Draw (gd) or ImageMagick (imagick) image processing library has to be enabled in the PHP configuration to generate thumbnails.

×

Notice

Simple Image Gallery Notice: It looks like PHP's 'GD Image Library' is not installed/enabled on your system. Please ask your hosting company to enable/install it.
Print
Category: Brewery
Hits: 1656

[sigplus] Critical error: The Graphics Draw (gd) or ImageMagick (imagick) image processing library has to be enabled in the PHP configuration to generate thumbnails.

As promised, sitting here cruising along at 28,000 feet, I am updating a few of these pages.  the brewing area/Bar is coming along very nicely.   I was originally planning on a different spot in the basement and at the last minute decided on using the corner I am using - hence all the extra crap that is pushed off to both sides at the moment.  Reason for that is the other spot that everything would get moved to is home to another project at the time, so space is very tight.

So far I have the front and side framed out, as well as the work surface on the side finished.  The working surface is two layers of 1/2 inch OSB that has been sanded and had four coats of polyurethane applied.  I went with two 1/2 inch pieces to add a little thickness over a single 3/4 piece.   The final coat will be applied once all surfaces are down - either another poly to seal all the seams etc.. or a coat of epoxy.

I mentioned the front of it was framed.   I had hoped to get the top work surface on it before this trip but ran out of time.  I had been leaving it open while I decided on what was going under the counter.   Most of the under counter area is going to be the keg cooler, most likely with room for bottles, as well as cooling for the soda gun system we are adding.   I am thinking that a water bath, cooled by the forced cold air, might work.  I would arrange it so the cooling air hit the water bath first, keeping it a bit cooler than the rest of the air.   My other alternative would be a DIY Glycol system, with the soda cold plate in the glycol bath and a heat exchanger/radiator to cool the beer-cooling-air. So, with all of those decisions up in the air, I kept it open - only to decide that I could finish the top and just build the cooler area from the inside.  Oh and to minimize the risk of damage, the bar top is going to be last.  I have decided that it will be a layer of caps under epoxy bartop finish.  I have approximately 1200 of the 2000 caps that I need to complete the surface, and will order the rest within a few weeks.

The last construction phase will be to get the "back" work area built up, probably after the rest is 100% complete. Under that section I will leave space for a dishwasher, for glassware and sanitizing bottles.

Somewhere in there, probaby between the bar top and the back section being built, the brewing parts need to be built - vent hood being the biggest part of that, followed by the electrical controls for the boil coil - and of course installing the coil into the kettle itself.

{gallery}brewarea1{/gallery}